Legislation Details

File #: 25-0293    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 12/26/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval to execute an interlocal agreement with Harris County Municipal Utility District No. 213-A in connection with the project known as ROW Acquisition - North Main St., Baytown - 2024, for the purpose of roadway construction, UPIN 24103MF3FY01, Precinct 3.
Sponsors: Mony Hossain
Attachments: 1. 25-0293-Partnership-ROW Acquisition-North Main St.- Baytown- PCT 3-24103MF3FY01 (2)
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): UPIN 24103MF3FY01
Vendor/Entity Legal Name (if applicable): Harris County Utility District No. 213-A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable):N/A
Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Harris County Municipal Utility District No. 213-A in connection with the project known as ROW Acquisition - North Main St., Baytown - 2024, for the purpose of roadway construction, UPIN 24103MF3FY01, Precinct 3.
end

Background and Discussion:
North Main Street Improvements include a reconstruction of the existing 2-lane asphalt roadway to a 4-lane concrete boulevard with underground storm sewer.

Expected Impact:
The construction of this project will allow for a better flow of traffic with the expansion from a 2- lane road to a 4-lane boulevard.

Alternative Options:
If not approved by Commissioner's Court; the Improvements of North Main Street would consist of designing a nonstandard boulevard where ROW is not acquired.


County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative ...

Click here for full text