File #: 25-0262    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/26/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval of change in contract No. 5 with Lecon, Inc., for the Lauder Stormwater Detention Basin - Phase 2, adding 48 calendar days (Greens Bayou Watershed, Bond ID C-34, Project ID P500-06-00-E006, Job No. 22/0224, Precinct 2, MWBE Contracted Goal: 17%, MWBE Current Participation: 48.1%).
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): P500-06-00-E006
Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWBE Contracted Goal (if applicable): 17%
MWBE Current Participation (if applicable): 48.1%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 5 with Lecon, Inc., for the Lauder Stormwater Detention Basin - Phase 2, adding 48 calendar days (Greens Bayou Watershed, Bond ID C-34, Project ID P500-06-00-E006, Job No. 22/0224, Precinct 2, MWBE Contracted Goal: 17%, MWBE Current Participation: 48.1%).
end

Background and Discussion:
This change in contract is needed to complete the construction contract for this project. Lauder Stormwater Detention Basin - Phase 2 includes excavating the southern compartment of a stormwater detention basin within the former Castlewood subdivision to reduce flooding along the P138-00-00 channel that drains to Greens Bayou. The purpose of this contract change is to adjust contract quantities for confirmed overruns, provide bollards to limit vehicular access, and extend contract time for inclement weather with zero total change in cost.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substa...

Click here for full text