Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): Harris County
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an interlocal hike and bike trail agreement with Harris County to construct and maintain a public hike and bike trail along both sides of HCFCD Units D100-00-00, D132-00-00, and D132-01-00, approximately 5.32 miles in length and 6 feet wide (Brays Bayou Watershed, Agreement No. 731, Precinct 4).
end
Background and Discussion:
Request for approval of an amendment to Interlocal Agreement No. 731 with Harris County to construct and maintain a public hike and bike trail along both sides of HCFCD Units D100-00-00, D132-00-00, and D132-01-00, approximately 5.32 miles in length and 6 feet wide. (Brays Bayou Watershed, Agreement No. 731)
Expected Impact:
By entering into this amended agreement with Harris County, it will allow Harris County to use a 3rd Party for construction and maintenance of the various recreational amenities on District right-of-way, including hike and bike trails.
Alternative Options:
If this interlocal agreement is not amended and executed, Harris County will not be able to contract out or partner with other entities for the design and construction of the proposed trail for use by the public.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distribute...
Click here for full text