Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 19102MF13501
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement (SOLS), for installation of an electric meter with CenterPoint Energy Houston Electric, LLC and authorize the County Auditor to pay monthly bills for 14127 1/2 Lillja Road Houston, TX 77060 (Aldine Village - Oak Glen Place West Subdivisions), including all deposit/fees for utility services, UPIN 19102MF13501, Precinct 2.
end
Background and Discussion:
The Aldine Village and Oak Glen Place West Subdivisions Drainage Improvements - 2018 project is located in Harris County, in Aldine near Halls Bayou. The scope of this project is to included storm sewer system upgrades, installation of storm sewer outfalls and detention basins with pump stations into Halls Bayou Channels P118-25 and P-118-26, driveway replacements, and related pavement work. This Utility Adjustment Agreement allows the project to move forward with the improvements as intended.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the Aldine Village and Oak Glen Place West subdivisions. This agreement allows for the proposed pump station to be serviced by Ce...