Primary Department: Toll Road Authority
Primary Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): RRP Consulting Engineers, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a First Amendment to the agreement with RRP Consulting Engineers, LLC, at no additional cost, to update the Scope of Services, update raw salary rates, replace Time of Performance, replace Indemnification, amend Delivery of Notices, amend Certificate of Interested Parties, add Additional Statutory Requirements, add Dispute Resolution, and replace Historically Underutilized Business Requirements to provide Construction Engineering and Inspection Services in support of the construction of the East Sam Houston Tollway from Interstate 10 (East) to SH 225, the Ship Channel Bridge Program, including the construction of twin bridges over the Houston Ship Channel (Precinct 2).
end
Background and Discussion:
On August 1, 2017 Commissioners Court approved an Agreement with S & B Infrastructure, Ltd. in the amount of $7,710,000 to provide Construction Engineering and Inspection Services in support of the construction of the East Sam Houston Tollway from Interstate 10 (East) to SH 225, the Ship Channel Bridge Program, including the construction of twin bridges over the Houston Ship Channel.
On June 27, 2023, the County approved the assignment of rights, duties and privileges of the Agreement to RRP Consulting Enginee...