Legislation Details

File #: 25-0091    Version: 1 Name:
Type: Investment Memo Status: Passed
File created: 12/23/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval of the Final Investment Memo for the Fire Marshal's Office Multi-Purpose Burn/Tactical Building and Flash Chamber project for an additional $2,200,000 for a total authorization of $2,600,000 and commercial paper funding for an additional $2,200,000 for a total allocation of $2,600,000.
Primary Department: Fire Marshal
Primary Department Head/Elected Official: Laurie L. Christensen, Fire Marshal

Secondary Department: County Engineer
Secondary Department Head/Elected Official: Dr. Milton Rahman

Regular or Supplemental RCA: Regular RCA

Type of Request: Investment Memo
Investment Memo Type: Final Investment Memo

Project Name: Multi-Purpose Burn-Tactical Building and Flash Chamber
Project ID (if applicable): FMO_BURN
Vendor/Entity Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Incremental Authorization Requested: $2,200,000
Total Estimated Project Cost: $2,600,000

Request Summary (Agenda Caption):
title
Request for approval of the Final Investment Memo for the Fire Marshal's Office Multi-Purpose Burn/Tactical Building and Flash Chamber project for an additional $2,200,000 for a total authorization of $2,600,000 and commercial paper funding for an additional $2,200,000 for a total allocation of $2,600,000.
end

Project Description:
A Multi-Purpose Burn/Tactical Building and Flash Chamber will be constructed at the Harris County Sheriff's and Fire Marshal's training facility located at 2318 Atascocita Rd, Humble TX. This project is for a multipurpose live fire, rescue, and tactical Burn Building and Flash Chamber that would facilitate advanced training of law enforcement, fire, emergency medical services (EMS), educational entities, and industrial partners. The total cost of the project is estimated to be $2,600,000. The project timeline for completion is estimated to be the second quarter of 2025. This is the request for the final distribution of $2,200,000 to complete the project.
The proposed building will be located at the FMO Atascocita Campus on th...