Title: Request for approval of a change in contract with First Class Units Inc, in connection with the Sheldon Health and Services Hub project, adding 14 calendar days with an addition in the amount of $7,850, Job No. 23/0376-1, UPIN 21289MF23B01, Precinct 1, MWBE Contracted Goal: 17%, MWBE Current Participation: 18.01%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Dr. Milton Rahman, Ph.D, P.E, PMP, CFM, ENV-SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official:

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 23/0376
Vendor/Entity Legal Name (if applicable): First Class Units Inc

MWBE Contracted Goal (if applicable): 17%
MWBE Current Participation (if applicable): 18.01%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with First Class Units Inc, in connection with the Sheldon Health and Services Hub project, adding 14 calendar days with an addition in the amount of $7,850, Job No. 23/0376-1, UPIN 21289MF23B01, Precinct 1, MWBE Contracted Goal: 17%, MWBE Current Participation: 18.01%.
end

Background and Discussion:
This contract with First Class Units, Inc. for construction services for the Sheldon Health Hub that consists of the renovation of the existing ROTC building on the campus of C.E. King MS at 8530 C. E. King Pkwy., Houston, TX 77044. This particular project HCPH will be leasing the existing ROTC building from Sheldon Independent School District on a long term basis.

The scope of work will include interior renovations of the existing facility with exterior improvements to fit the programmatic goals and functional needs of the facility.

Changes included here involve: additional demo and make-safe of obsolete plumbing, high-voltage electrical, and air vent connections not originally captured in base bid.



Expected Impact:
These changes allow the contractor to bill for required changes resulting from unforeseen conditions and Owner Requests.


Alternative Options:
Should we ...