Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 19101MF14202
Vendor/Entity Legal Name (if applicable): Equistar Chemicals, LP
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a utility agreement with Equistar Chemicals, LP in connection with Pine Trails Subdivision Drainage Improvements - 2018, UPIN 19101MF14202, Precinct 2.
end
Background and Discussion:
The Pine Trails Subdivision project is located in Northeast Harris County in Precinct 2. The scope of work for this utility agreement includes Harris County's installation of a 36" reinforced concrete pipe within Equistar's easement. This agreement will allow Harris County to perform the installation work.
Expected Impact:
This project generally seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This utility agreement specifically will allow Harris County to install a 36" reinforced concrete pipe to direct flow from the subdivision into the detention basin. No impact to project schedule or staffing anticipated.
Alternative Options:
Alternative options would include redesign of the project to avoid the easement or abandonment of the project.
County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: H: Improve the condition and resilience o...