Legislation Details

File #: 25-0072    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/22/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval of a change in contract with Builders United, LLC., in connection with final construction of Dennis Johnston Park, Cabin 2 - 2019, with an addition in the amount of $650.00, Job No. 22/0337-2, UPIN 20104MF1E901, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation Goal: 25.15%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0337, UPIN 20104MF1E901
Vendor/Entity Legal Name (if applicable): Builders United, LLC

MWBE Contracted Goal (if applicable): 26%
MWBE Current Participation (if applicable): 25.15%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Builders United, LLC., in connection with final construction of Dennis Johnston Park, Cabin 2 - 2019, with an addition in the amount of $650.00, Job No. 22/0337-2, UPIN 20104MF1E901, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation Goal: 25.15%.
end

Background and Discussion:
Project includes reconstruction of Cabin 2 at Dennis Johnston Park for Harris County Precinct 3.

This change in contracts includes the final adjustment (reconciliation of actual quantities used in construction against the bid quantities). ($650.00).

Expected Impact:
Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated.

Alternative Options:
Maintain the original scope of the project.




County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A

Additional notes related to the Strategic Plan: N/A

Prior Court Action (if any):
Date
Ag...

Click here for full text