Legislation Details

File #: 24-7689    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 11/27/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Centennial Contractors LLC, for the HCCO Civil Courthouse Level 3, 6, & 7 Renovation project, UPIN 23515MF2N801, Precinct 1, MWDBE Contracted Goal: 18.37%, MWDBE Current Participation: 38.51%.
Attachments: 1. 24_0815-G704 - Certificate of Substantial Completion - HC CO Renovation 1
Department: County Engineer
Department Head/Elected Official: Dr. Milton Rahman, Ph.D, P.E, PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): 22/0454
Vendor/Entity Legal Name (if applicable): Centennial Contractors Enterprises, Inc.

MWDBE Contracted Goal (if applicable): 18.37%
MWDBE Current Participation (if applicable): 38.51%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Centennial Contractors LLC, for the HCCO Civil Courthouse Level 3, 6, & 7 Renovation project, UPIN 23515MF2N801, Precinct 1, MWDBE Contracted Goal: 18.37%, MWDBE Current Participation: 38.51%.
end

Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date is important for all governmental entities as outlined in the GASB Statement #34, Capital Assets and Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.

Completion Date for this project is established to be August 15th, 2024.

Expected Impact:
This action establishes the date on which a capital improvement enters service as a Harris County asset.

Alternative Options:
N/A

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
03-08-2023
151
Approval of FIM for the Count...

Click here for full text