Legislation Details

File #: 24-7597    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/26/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of change in contract No. 3 with Rebel Contractors, Inc., for the Mud Gully Channel Conveyance Improvements Package 2, adding 22 calendar days (Clear Creek Watershed, Bond ID C-03, Project ID A120-00-00-C004, Job No. 20/0244A, Precinct 2, project was awarded prior to launch of County's W/WBE Program).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): A120-00-00-C004
Vendor/Entity Legal Name (if applicable): Rebel Contractors, Inc.

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 3 with Rebel Contractors, Inc., for the Mud Gully Channel Conveyance Improvements Package 2, adding 22 calendar days (Clear Creek Watershed, Bond ID C-03, Project ID A120-00-00-C004, Job No. 20/0244A, Precinct 2, project was awarded prior to launch of County's W/WBE Program).
end

Background and Discussion:
Mud Gully Channel Conveyance Improvements Package 2 includes clearing and grubbing, excavating, and disposing of material, constructing concrete channel lining, and removing and replacing storm sewer system components. This contract change is needed to adjust the quantities for concrete channel lining, headwalls, wingwalls, and excavation to reflect the actual amount of work required. 22 additional days are needed to extend the contract duration to complete this additional work. There will be $0 change in contract value, as the additional costs are being offset by removing items no longer required.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

Alignment with Goal(s):
_ Justice and S...

Click here for full text