Legislation Details

File #: 24-7593    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/26/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of change in contract No. 1 with Solid Bridge Construction, LLC, for the Meyergrove Detention Basin, adding 48 calendar days (Brays Bayou Watershed, Bond ID Z-02, Project ID D500-11-00-E001, Job No. 23/0306, Precinct 1, MWDBE Contracted Goal: 32%, MWDBE Current Participation: 69.4%).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): D500-11-00-E001
Vendor/Entity Legal Name (if applicable): Solid Bridge Construction, LLC

MWDBE Contracted Goal (if applicable): 32%
MWDBE Current Participation (if applicable): 69.4%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 1 with Solid Bridge Construction, LLC, for the Meyergrove Detention Basin, adding 48 calendar days (Brays Bayou Watershed, Bond ID Z-02, Project ID D500-11-00-E001, Job No. 23/0306, Precinct 1, MWDBE Contracted Goal: 32%, MWDBE Current Participation: 69.4%).
end

Background and Discussion:
The Meyergrove Detention Basin includes the construction of the D500-11-00 Stormwater Detention Basin as well as a maintenance access path. The purpose of this contract change is to add 48 days (20 days for inclement weather days incurred beyond the original contract allotment and 28 days for testing and disposal of treatment plant effluent that overflowed into the basin.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
09/19/2023
326.
Award

Location: N/A
Address (if applicable):
Precinct(...

Click here for full text