Legislation Details

File #: 24-7592    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/26/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of change in contract No. 2 with Arrowstone Contracting, LLC, for the Mercer Stormwater Detention Basin, adding 63 calendar days and resulting in an addition of $105,335 to the contract amount (Cypress Creek Watershed, Bond ID F-88, Project ID K500-21-00-E001, Job No. 23/0315, Precinct 1, MWDBE Contracted Goal: 16%, MWDBE Current Participation: 10.12%).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): K500-21-00-E001
Vendor/Entity Legal Name (if applicable): Arrowstone Contracting, LLC

MWDBE Contracted Goal (if applicable): 16%
MWDBE Current Participation (if applicable): 10.12%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 2 with Arrowstone Contracting, LLC, for the Mercer Stormwater Detention Basin, adding 63 calendar days and resulting in an addition of $105,335 to the contract amount (Cypress Creek Watershed, Bond ID F-88, Project ID K500-21-00-E001, Job No. 23/0315, Precinct 1, MWDBE Contracted Goal: 16%, MWDBE Current Participation: 10.12%).
end

Background and Discussion:
The purpose of this contract change is to extend the concrete channel lining to match the actual quantities required to complete the original scope and to adjust the contract duration by adding 63 days (30 days for the modified scope of work and 33 days for weather-related delays). There is available budget in this project to cover the additional costs.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
10/10/2023
305.
Award
0...

Click here for full text