Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN - 19104MF13401 - Job No. 23/0074
Vendor/Entity Legal Name (if applicable): Specialty Construction TX, LLC
MWDBE Contracted Goal (if applicable): 27.00%
MWDBE Current Participation (if applicable): 10.71%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with Fallbrook, Ridgepoint, and Westpoint Subdivisions Drainage Improvements - 2018, adding 1 calendar day, with no change in the amount, Job No. 23/0074-05, UPIN 19104MF13401, Precinct 2, MWDBE Contracted Goal: 27.00%, MWDBE Current Participation: 10.71%.
end
Background and Discussion:
The location of the work is in the Fallbrook, Ridgepoint, and Westpoint Subdivisions in the Halls Bayou Watershed. The proposed improvements include installation of a new storm sewer system, roadway paving, channel restoration and desilting.
The Change in contract is needed to add new items to reconcile new line items with the underrunning items of the contract. The following quantity adjustments are required:
* New line items #101 and 102 need to be added for an additional amount of $2,658.00 and 1 day.
* To offset, underrunning line item #82 will be decreased for a deduction in the amount of $2,658.00.
* The above additions and deductions resulted in a net addition to the contract in the amount of $0.00 and 1 calendar day.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation
of structural flood damage to homes in the Fallbrook, Ridgepoint and Westpoint subdivision.
Alternative Options:
The County could elect to fund the requested task ...
Click here for full text