Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN - 23208MF2TN01 - Job No. 23/0178
Vendor/Entity Legal Name (if applicable): Reliance Construction Services, L.P.
MWDBE Contracted Goal (if applicable): 24%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place (Phase II) Subdivision Drainage Improvements - 2018, with an addition in the amount of $114,307.76, Job No. 23/0178-1, UPIN 23208MF2TN01, Precinct 2, MWDBE Contracted Goal: 24%, MWDBE Current Participation: 100%.
end
Background and Discussion:
The Beaumont Place Subdivision is located in the Greens Bayou watershed near Highway 90 and Beltway 8. The proposed improvements include roadside ditch regrading, driveway culvert upgrades, expansion of channel along Big Gulch, concrete lined Sulphur Gully channel with reinforced concrete box (RCB) crossing improvements. Improvements also include multiple detention ponds along Big Gulch with an extreme event overflow swale towards the upstream portion of the channel.
The Change in Contract includes the following:
* Quantity Adjustment: The addition of quantities reconciles actual quantities used in construction with the estimated quantities for completing the proposed scope of work. Items 5, 9, 17, 22, 23, 26, 30, 32, 37, 38, 40, 68, 114, 140, 142, 154, and 198 were increased for an addition in the amount of $228,408.52. Items 27, 141, and 143 were decreased for a deduction in the amount of $140,771.00.
* New Item 201 Reinforced Concrete Sidewalk and Item 202 Concrete Pavement (8") were added for an addition in the amount of $26,670....
Click here for full text