Legislation Details

File #: 24-7493    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/24/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of a change in contract with E.P. Brady, Ltd., in connection with Kingslake Forest Subdivision Drainage Improvements, with no change in the amount, Job No. 22/0348-1, Grant Fund, UPIN 19101MF17A01, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 100%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN - 19101MF17A01 - Job No. 22/0348
Vendor/Entity Legal Name (if applicable): E.P. Brady, Ltd.

MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with E.P. Brady, Ltd., in connection with Kingslake Forest Subdivision Drainage Improvements, with no change in the amount, Job No. 22/0348-1, Grant Fund, UPIN 19101MF17A01, Precinct 1, MWDBE Contracted Goal: 20%, MWDBE Current Participation: 100%.
end

Background and Discussion:
Kingslake Forest Subdivision located in Northeast Harris County, Texas, Precinct 1. Under existing conditions, the Kingslake Forest Subdivision has experienced flood damage during extreme rainfall events. The project will include storm sewer improvements along multiple streets in the neighborhood. The proposed drainage improvements will consist of removal and replacement of existing storm sewers, as well as replacement of the inlets. A detention basin will also be added to the southeastern portion of the neighborhood, to mitigate for the impacts to Greens Bayou tributary P127-00-00 from the improvements. This detention basin will be dry bottom basin, with a perimeter concrete trail. The basin may include recreational features such as trees, signage, trash receptables, and benches.

The Change in Contract includes the following:

* Quantity Adjustment: The addition of quantities reconciles actual quantities used in construction with the estimated quantities for completing the proposed scope of work. Items 5, 12, 22, and 89 were increased for an addition in the amount of $35,686.25. Items 1, 41, and...

Click here for full text