Legislation Details

File #: 24-7492    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/24/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of a change in contract with R Construction Civil, LLC, in connection with Pine Trails Subdivision Drainage Improvements - 2018, with an addition in the amount of $248,896.10, Job No. 23/0073-01, UPIN 19101MF14201, Precinct 2, MWDBE Contracted Goal: 27%, MWDBE Current Participation: 16.44%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 23/0073; UPIN: 19101MF14201
Vendor/Entity Legal Name (if applicable): R Construction Civil, LLC

MWDBE Contracted Goal (if applicable): 27%
MWDBE Current Participation (if applicable): 16.44%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with R Construction Civil, LLC, in connection with Pine Trails Subdivision Drainage Improvements - 2018, with an addition in the amount of $248,896.10, Job No. 23/0073-01, UPIN 19101MF14201, Precinct 2, MWDBE Contracted Goal: 27%, MWDBE Current Participation: 16.44%.
end

Background and Discussion:
Pine Trails Subdivision is in Northeast Harris County, Texas, Precinct 2 (redistricted from Precinct 1). The subdivision consists of approximately 525 acres and 1,800 homes. The residents have experienced structural flooding during several recent flood events. Approximately 264 homes were reported to have flooded during Hurricane Harvey. The purpose of this project is to reduce flooding for homes within the subdivision. The proposed solution includes upgrading storm sewers and adding 3 detention ponds. This contract includes construction services for the Phase 3 and 4 construction phases.

The change in contract is needed to reconcile the overrunning line items and adding new line item to the contract. Below is a summary of changes:

* The increase of quantities on installation of line Items (item # 8, 12, 28, 36, 44, 58, 124, 127 and 128) for an addition in the amount of $239,656.10.

* Added new line Item # 164 - Additional redwood headers in the pavement for an additional cost in the amount of $9,240.00.

* This will result in a total addition in the amount of $248,896.10 an...