Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN - 19101MF13601 - Job No. 23/0028
Vendor/Entity Legal Name (if applicable): Reytec Construction Resources, Inc.
MWDBE Contracted Goal (if applicable): 21%
MWDBE Current Participation (if applicable): 25.10%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Reytec Construction Resources, Inc., in connection with Oak Glen Place Subdivision Drainage Improvements - 2018, with no change in the amount, Job No. 23/0028-05, UPIN 19101MF13601, Precinct 2, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 25.10%.
end
Background and Discussion:
The location of the work is in the Oak Glen Place (East) subdivision in the Halls Bayou Watershed. The proposed improvements include installation of a new storm sewer system, driveways paving, widening, and regrading of existing roadside ditches, and construction of a new detention pond.
The Change in contract includes the following:
Quantity Adjustment: The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.
* The increase of quantities on overrun Line Items# 21 and 22 for an addition in the amount of $13, 945.40.
* Added new line items #152 and #153 for an addition in the amount of $11,206.18.
* The decrease of quantities on underrun Line Items# 65, 67 and 130 for a deduction in the amount of $25,151.58.
The above additions and deductions resulted in a net addition to the contract in the amount of $0.00 and 0 calendar days.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage ...