Legislation Details

File #: 24-7438    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/22/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements Project, adding 7 calendar days, Job No. 23/0278-02, Grant Fund, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 34.63%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19102MF17801; Job No: 23/0278-02
Vendor/Entity Legal Name (if applicable): CE Barker Ltd.

MWDBE Contracted Goal (if applicable): 26%
MWDBE Current Participation (if applicable): 34.63%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements Project, adding 7 calendar days, Job No. 23/0278-02, Grant Fund, UPIN 19102MF17801, Precinct 3, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 34.63%.
end

Background and Discussion:
Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements project is in the Northeast area of Harris County, east of FM 2100 and north of FM 1942. The scope of this project includes regrading roadside ditches, replace undersized driveway culverts, removal and replacement of driveways, road replacement in certain sections and construction of a dry bottom detention basin with pump station on the northeast corner of the subdivision, south of East Broussard.

The Change in contract is needed to reconcile the overrunning items with the underrunning items of the contract and adding additional days to the contract. The following quantity adjustments are required:

* The increase of quantities for line items # 3 and 5 for an addition in the amount of $84,705.01.
* The decrease of quantities for line items # 12,24,28,50,57,74 and 79 for a deduction in the amount of $84,705.01.

The above additions and deductions result in a net change in the amount of $0.00 and 7 calendar days.

Expected Impact:
This project seeks ...