Legislation Details

File #: 24-7433    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/22/2024 In control: Commissioners Court
On agenda: 12/10/2024 Final action: 12/10/2024
Title: Request for approval of a change in contract with D & W Contractors, Inc., in connection with Sidewalk - Woodforest Boulevard Phase II - 2022, adding 3 calendar days, with an addition in the amount of $10,386.00, Job No. 24/0018-2, UPIN 22102MF28U02, Precinct 2, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 49.95%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0018, UPIN 22102MF28U02
Vendor/Entity Legal Name (if applicable): D & W Contractors, Inc.

MWDBE Contracted Goal (if applicable): 26%
MWDBE Current Participation (if applicable): 49.95%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with D & W Contractors, Inc., in connection with Sidewalk - Woodforest Boulevard Phase II - 2022, adding 3 calendar days, with an addition in the amount of $10,386.00, Job No. 24/0018-2, UPIN 22102MF28U02, Precinct 2, MWDBE Contracted Goal: 26%, MWDBE Current Participation: 49.95%.
end

Background and Discussion:
This project consists of the construction of approximately 11,400 linear feet of 6-foot-wide sidewalks along north and south Woodforest Boulevard. The project limits are from Redstone Street to Freeport Street.

This change order includes the following:
- While removing the existing ramp at the intersection of Castlebar Court and Woodforest Boulevard, the contractor uncovered a sinkhole caused by erosion of the soil beneath the roadway. The affected areas measure approximately 4 x 3 feet and 6 x 4 feet where soil has been washed out. The engineer of record has recommended the use of flowable fill to restore the stability of the roadway and address the underlying erosion. This change order will add $1,800.00 to the contract with no additional days.
- Due to the shortage of 5-inches Cedar Elm trees and the significant cost increase associated with sourcing them from out of state, it has been decided to use an alternative tree species. The engineer of record recommends substituting with Live Oak trees to maintain project timelines and budget. This change ...

Click here for full text