Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 24102MF3K601
Vendor/Entity Legal Name (if applicable): City of Seabrook
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute an Interlocal agreement with the City of Seabrook for the full study, design, and construction cost estimate only for the proposed reconstruction of 6,200 linear feet of roadway in connection with Road Improvements - North Meyer - 2024, UPIN 24102MF3K601, Precinct 2.
end
Background and Discussion:
The project is a full study, design, and construction cost estimate only for the proposed reconstruction of 6,200 linear feet of roadway of North Meyer from SH 146 to E. Meyer in the City of Seabrook, transitioning from asphalt to concrete pavement and drainage improvement.
Expected Impact:
Enhance the durability, longevity, and sustainability of the roadway infrastructure.
Alternative Options:
The alternative option would be to explore other funding options, or to fully fund through Harris County.
Alignment with Goal(s):
X Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
Location: North Meyer from SH 146 to E. Meyer in the City of Seabrook, TX 77586
Address (if applicable):
Precinct(s): Precinct 2
Fiscal and Personnel Summary
Service Name
Current Fiscal Year Cost
Annual Fiscal Cost
Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
Existing Budget
1070 - Mobility Fund
$
$500,000.00
$500,000.00
$
Choose an item.
$
$
$
$
Choose an item.
...
Click here for full text