Title: Request for approval to execute an agreement with Page Southerland Page, Inc., in the amount of $242,690.00, for Professional Architectural/Engineering design services in connection with Meyer Park - 7700 Cypresswood Dr., Spring, TX 77379 and Dyess Park-16822 Kitzman Rd., Cypress, TX 77429, UPIN 24103MF3G401, Precinct 3, MWDBE Contracted Goal: 19.6%, MWDBE Current Participation: 46.63%.
Attachments: 1. 24-7246-Award-24103MF3G401 Meyer Park and Dyess Park, Page Southerland Page, P3.10312024.v02
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 24103MF3G401
Vendor/Entity Legal Name (if applicable): Page Southerland Page

MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): 46.63%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Page Southerland Page, Inc., in the amount of $242,690.00, for Professional Architectural/Engineering design services in connection with Meyer Park - 7700 Cypresswood Dr., Spring, TX 77379 and Dyess Park-16822 Kitzman Rd., Cypress, TX 77429, UPIN 24103MF3G401, Precinct 3, MWDBE Contracted Goal: 19.6%, MWDBE Current Participation: 46.63%.
end

Background and Discussion:
Precinct 3 submitted a request to HCED PMO for HCED to manage the design and construction of the renovation or replacement of three restroom/concession facilities at Meyer Park and one restroom facility at A.D. Dyess Park. Not all of the existing facilities provides ADA accessible stalls, and they all experience poor air circulation. The existing facilities are not freeze resistant and plumbing fixtures have failed and been replaced after past weather events. The Prime Consultant will provide professional architectural and engineering services for to provide high-quality amenities to the existing facilities, including replacing plumbing, and adding HVAC.


Expected Impact:
This award of this project will allow the firm to conduct the necessary design for the construction to the existing restroom/concession facilities at Precinct 3, making the facilities resilient, accessible, hospitable, and ultimately updating the appearance of the park facilities.


Alternative Options:
If no action is taken, the existing stru...