File #: 24-7244    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/1/2024 In control: Commissioners Court
On agenda: 11/12/2024 Final action: 11/12/2024
Title: Request for approval of a change in contract with DT Construction, LP, in connection with Harris County Pollution Control Renovation, located at 101 S. Richey St., Suite H., Pasadena, TX 77506, adding 91 calendar days, with an addition in the amount of $4,239.91, Job No. 22/0283, UPIN 21272MF22601, Precinct 2, MWDBE Contracted Goal: 15.2%, MWDBE Current Participation: 15.2%.
Department: County Engineer
Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 22/0283
Vendor/Entity Legal Name (if applicable): DT Construction

MWDBE Contracted Goal (if applicable): 15.2%
MWDBE Current Participation (if applicable): 15.2%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DT Construction, LP, in connection with Harris County Pollution Control Renovation, located at 101 S. Richey St., Suite H., Pasadena, TX 77506, adding 91 calendar days, with an addition in the amount of $4,239.91, Job No. 22/0283, UPIN 21272MF22601, Precinct 2, MWDBE Contracted Goal: 15.2%, MWDBE Current Participation: 15.2%.
end

Background and Discussion:
This project was approved on Commissioners Court on 10/13/2020. Improvements include interior renovation of the office suite, adding emergency shower drains, and upgrading the laboratory suite to 100% operational during a disaster event, which includes a water tank for domestic water and a new 1000 kW emergency generator for electricity.

This change in contract provides additional general conditions as well as necessary materials, equipment and labor for install sediment trap at generator gas line and painting of gas line, and additional requirements by the City of Pasadena. This comes to a total of $4,239.91 and additional 91 calendar days.

Expected Impact:
Upon completion of the project, Harris County Pollution Control Services will be able to maintain full operations during major disaster and storm events. The requested changes allow the completion of the project in accordance with the original intent of the project.

Alternative Options:
Commissioner court could postpone the change order, which would postpone the completion of th...