File #: 24-7207    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 11/1/2024 In control: Commissioners Court
On agenda: 11/12/2024 Final action: 11/12/2024
Title: Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final construction of Water Distribution System - Parkwood Estates Ph 3 Apala Dr - 2021, with a deduction in the amount of $399,330.66, Job No. 22/0423-2, UPIN 21289MF1Y601, Precinct 2, MWDBE Contracted Goal: 24%, MWDBE Current Participation: 100%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0423, UPIN 21289MF1Y601
Vendor/Entity Legal Name (if applicable): Reliance Construction Services, LP

MWDBE Contracted Goal (if applicable): 24%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Reliance Construction Services, LP, in connection with final construction of Water Distribution System - Parkwood Estates Ph 3 Apala Dr - 2021, with a deduction in the amount of $399,330.66, Job No. 22/0423-2, UPIN 21289MF1Y601, Precinct 2, MWDBE Contracted Goal: 24%, MWDBE Current Participation: 100%.
end

Background and Discussion:
Parkwood Estates Phase 3 includes construction of a new water distribution system at Apala Drive with Installation of water distribution line, fire hydrants, providing water connection to the eligible resident and decommissioning of private water wells. This change in contract includes the final reconciliation of actual quantities used in construction against the bid quantities. Total = (-$399,330.66)

Expected Impact:
This action allows for unused funds to be returned to Harris County.

Alternative Options:
Action required to return unused funds.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
X Public Health
_ Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
03/14/2023
23-1462
Contract Award
05/07/2024
24-2614
Contract Amendment #1 for extension of project term

Location:
Address (if applicable):
Precinct(s): Precinct 2

Fiscal and Personnel Summary
Service Name
Engineering


Current Fiscal Year Cost
...