Legislation Details

File #: 24-6820    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 10/17/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Request for approval to execute a Joint Participation Interlocal Agreement with the City of South Houston for traffic signal rebuild design at the intersection of College Avenue at Main Street and the intersection of College Avenue at Austin Street, UPIN 24035MF34Z01, Precinct 2.
Sponsors: Mony Hossain
Attachments: 1. 24-6820-Partnership-UPIN-UPIN 24035MF34Z01- Traffic Signal at intersection -Pct 2-10.17
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): UPIN 24035MF34Z01
Vendor/Entity Legal Name (if applicable): City of South Houston

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to execute a Joint Participation Interlocal Agreement with the City of South Houston for traffic signal rebuild design at the intersection of College Avenue at Main Street and the intersection of College Avenue at Austin Street, UPIN 24035MF34Z01, Precinct 2.
end

Background and Discussion:
Traffic signals are re-built to improve the operation of an intersection and better facilitate pedestrian activities. The existing signals use outdated and degrading equipment and do not accommodate pedestrian crossings. Re-building these signals will ensure the two intersections are brought up to compliance with current standards and provide pedestrian connectivity.

Expected Impact:
Re-building the traffic signals will bring the infrastructure to current standards, specifications, and reduce overall maintenance cost. It will also significantly reduce the risk of failure during a catastrophic event.

Alternative Options:
Maintain the existing traffic signal and slowly replace degrading parts as they fail. This may potentially be more costly and incurs a risk of failure due to aging infrastructure.

Alignment with Goal(s):
x Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
x Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken




Location
Address (if applicable): : Traffic Signal at intersection of College Avenue and Beaumont...

Click here for full text