Legislation Details

File #: 24-6759    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/17/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Request for approval of change in contract No. 4 with Lecon, Inc., for the Keegans Bayou - General Repairs - US 59 to South Dairy Ashford Road, adding 61 calendar days (Brays Bayou Watershed, Project ID D118-00-00-X009, Job No. 22/0091, Precinct 4, MWDBE Contracted Goal: 27.85%, MWDBE Current Participation: 20.21%).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): D118-00-00-X009
Vendor/Entity Legal Name (if applicable): Lecon, Inc.

MWDBE Contracted Goal (if applicable): 27.85%
MWDBE Current Participation (if applicable): 20.21%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 4 with Lecon, Inc., for the Keegans Bayou - General Repairs - US 59 to South Dairy Ashford Road, adding 61 calendar days (Brays Bayou Watershed, Project ID D118-00-00-X009, Job No. 22/0091, Precinct 4, MWDBE Contracted Goal: 27.85%, MWDBE Current Participation: 20.21%).
end

Background and Discussion:
The purpose of this contract change is to add 61 calendar days to the contract duration and no change to the project budget. This change in contract is needed to complete the construction contract for this project. Keegans Bayou-General Repairs-US 59 to S Dairy Ashford includes Erosion Repairs Between US 59 and South Dairy Ashford Road for the Harris County Flood Control District.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
09/14/2022
205.
Award
06/27/2023
125.
Change in Contract No. 1
02/2...