Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): Z100-00-00-P013
Vendor/Entity Legal Name (if applicable): AIG Technical Services, LLC
MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of an agreement with AIG Technical Services, LLC, in the amount of $500,000, for engineering services to provide hydrologic and hydraulic analyses for Flood Control District projects (Project ID Z100-00-00-P001, Agreement No. 2024-49, Countywide, MWDBE Contracted Goal: 19.6%).
end
Background and Discussion:
This agreement will allow AIG to provide additional hydrologic and hydraulic (H&H) support for flood risk reduction projects and drainage impact reviews at times when there are a large volume of analyses to complete and there are not enough existing staff resources.
Expected Impact:
This H&H on-call contract will help reduce review time by adding additional capacity.
Alternative Options:
If not approved there will be schedule delays for multiple projects that would otherwise be served by this agreement.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
07/15/2024
124.
ATN
Location: N/A
Address (if applicable):
Precinct(s): Countywide
Fiscal and Personnel Summary
Service Name
4.a.8 - Hydrologic Services
Current Fiscal Year Cost
Annual Fiscal Cost
Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
Existing Budget
Tax Revenue - FCD
$
$500,000
$500,000
$
Choose an item.
$
$
$
$
Choose an item.
$
$
$
$
Total Curre...
Click here for full text