Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): 24102MF34401
Vendor/Entity Legal Name (if applicable): ExxonMobil Pipeline Company LLC
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a Consent Agreement with ExxonMobil Pipeline Company LLC (EMPCo) to construct an existing sidewalk replacement involving the removal of a 6' asphalt trail and replacing with an 8' wide concrete sidewalk across its pipeline easement, UPIN 24102MF34401, Precinct 2.
end
Background and Discussion:
The project includes the construction of approximately 8677 LF replacing existing 6' trail to 8' wide asphalt Hike and Bike Trail with Concrete. The project limits are from Scarsdale Blvd to Blackhawk Blvd. A section of proposed Trail close to Blackhawk Blvd crosses ExxonMobil easement, Harris County requested for letter of no Objection. ExxonMobil has agreed for the construction and provided a Right-of-Way Consent Agreement with terms and conditions mentioned.
Expected Impact:
This action allows the continuation of the contracted work and provides bikers a continuous trail from Scarsdale Blvd to Blackhawk Blvd.
Alternative Options:
If no action is taken, the project may experience construction delays, there will be a trail gap at the utility easement, and the intended objective will not be achieved.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
N/A
N/A
N/A
Location: from Scarsdale Blvd to Blackhawk Blvd.
Address (if appl...
Click here for full text