Title: Request for approval to execute an amendment with Brooks & Sparks, Inc., in the amount of $130,660.20 for professional engineering services to provide improvements to Telge Road Segment 6 - from 300-ft North of Grant Road to 690-ft North of SH99 - 2014, UPIN 15104MF0DN03, Precinct 3, MWDBE Contracted Goal: 19.60%, MWDBE Current Participation: 57.28%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 15104MF0DN03
Vendor/Entity Legal Name (if applicable): Brooks & Sparks, Inc.

MWDBE Contracted Goal (if applicable): 19.60%
MWDBE Current Participation (if applicable): 57.28%
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval to execute an amendment with Brooks & Sparks, Inc., in the amount of $130,660.20 for professional engineering services to provide improvements to Telge Road Segment 6 - from 300-ft North of Grant Road to 690-ft North of SH99 - 2014, UPIN 15104MF0DN03, Precinct 3, MWDBE Contracted Goal: 19.60%, MWDBE Current Participation: 57.28%.
end

Background and Discussion:
This amendment includes a variety of changes to the design including the addition of an interim right turn lane at the Grand Parkway, a phase 2 environmental site assessment, as well as modifications to the traffic signal designs due to a recent alignment adjustment.

Expected Impact:
This amendment will allow the construction of an interim right turn lane to improve traffic flow at the Grand Parkway. The phase 2 environmental site assessment includes soil sampling that will determine if any soil near the gas station in the project limits has been contaminated. The amendment will also allow the traffic signals to be adjusted to reflect the recent alignment change.

Alternative Options:
An alternative would be to not design the interim right turn lane, not to conduct the phase 2 environmental site assessment, or not to modify the traffic signals to reflect the new alignment all resulting a less than desirable project.

Alignment with Goal(s):
_ Justice and Safety