Department: Toll Road Authority
Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): Scientech Engineers, Inc.
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a First Amendment to the agreement with Scientech Engineers, Inc. to update the Scope of Services, increase compensation and payment by $495,000 to replace lump sum language with hourly billing, increase Time and Performance, replace Indemnification, amend Delivery of Notices, add Historically Underutilized Business Requirements, and replace Appendix B Maximum Raw Salary Rates, for final bridge design of the SH 225 eastbound to Sam Houston Tollway (SHT) southbound direct connector and the SHT southbound to SH 225 westbound direct connector between East Sam Houston Tollway and SH 225 (Precinct 2).
end
Background and Discussion:
On October 9, 2018, Commissioners Court approved an Agreement with Scientech Engineers, Inc. in the amount of $1,126,000 for final bridge design of the SH 225 eastbound to Sam Houston Tollway (SHT) southbound direct connector and the SHT southbound to SH 225 westbound direct connectors between East Sam Houston Tollway and SH 225.
The original Agreement is being amended to increase payment from $1,126,000 to $1,621,000.
The December 18, 2018, Commissioners Court authorized negotiations with the Texas Department of Transportation (TxDOT) for the design and construction of two partial interchanges - Tomball Tollway at Grand Parkway and Sam Houston Tollway at State Highway 225. On February 23, 2023, the Texas Transportation Commission authorized the connection of the Sam Houston Tollway at State Highway 225 ...