Department: Toll Road Authority
Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): E18-0349
Vendor/Entity Legal Name (if applicable): Atser, LP
MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Atser, LP for construction materials testing and geotechnical engineering services for the SH 225 and Sam Houston Tollway East partial interchange construction project in the amount of $2,000,000 (Precinct 2, MWDBE Contracted Goal: 19.6%).
end
Background and Discussion:
Construction materials testing is needed for the SH 225 and Sam Houston Tollway East Partial Interchange construction project. Atser, LP was selected and will be responsible for performing the sampling and materials testing service for the SH 225 and Sam Houston Tollway East partial interchange construction project.
On August 27, 2024, Commissioners Court approved a request to negotiate an Agreement with Atser, LP for construction materials testing and geotechnical engineering services for the SH 225 and Sam Houston Tollway East partial interchange construction project.
On August 6, 2024 Commissioners Court Awarded the construction project to Zachry Construction Corporation.
Expected Impact:
Funding for this request will come from the Toll Road Authority. Approval of this request will permit HCTRA to support to system planning, engineering, sustainability, and tolling for customers as well as communities within Harris County.
Alternative Options:
No other recommended services for this identified need.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation