Legislation Details

File #: 24-6647    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 10/15/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Request for approval to execute an agreement with Atser, LP for construction materials testing and geotechnical engineering services for the SH 225 and Sam Houston Tollway East partial interchange construction project in the amount of $2,000,000 (Precinct 2, MWDBE Contracted Goal: 19.6%).
Attachments: 1. 22-6647 ATSER_-_CMT_AGREEMENT_(225_Interchange)
Department: Toll Road Authority
Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): E18-0349
Vendor/Entity Legal Name (if applicable): Atser, LP

MWDBE Contracted Goal (if applicable): 19.6%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Atser, LP for construction materials testing and geotechnical engineering services for the SH 225 and Sam Houston Tollway East partial interchange construction project in the amount of $2,000,000 (Precinct 2, MWDBE Contracted Goal: 19.6%).
end

Background and Discussion:
Construction materials testing is needed for the SH 225 and Sam Houston Tollway East Partial Interchange construction project. Atser, LP was selected and will be responsible for performing the sampling and materials testing service for the SH 225 and Sam Houston Tollway East partial interchange construction project.

On August 27, 2024, Commissioners Court approved a request to negotiate an Agreement with Atser, LP for construction materials testing and geotechnical engineering services for the SH 225 and Sam Houston Tollway East partial interchange construction project.

On August 6, 2024 Commissioners Court Awarded the construction project to Zachry Construction Corporation.

Expected Impact:
Funding for this request will come from the Toll Road Authority. Approval of this request will permit HCTRA to support to system planning, engineering, sustainability, and tolling for customers as well as communities within Harris County.

Alternative Options:
No other recommended services for this identified need.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governanc...