Legislation Details

File #: 24-6556    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/14/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Request for approval of a change in contract with McKenna Contracting, Inc., in connection with final construction of Binford Circle Park Playground - 2022, adding 116 calendar days, with no change in the amount, Job No. 23/0086-1, UPIN 23104MF2UD01, Precinct 4, MWDBE Contracted Goal: 11%, MWDBE Current Participation: 100%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No: 23/0086, UPIN 23104MF2UD01
Vendor/Entity Legal Name (if applicable): McKenna Contracting, Inc.

MWDBE Contracted Goal (if applicable): 11%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with McKenna Contracting, Inc., in connection with final construction of Binford Circle Park Playground - 2022, adding 116 calendar days, with no change in the amount, Job No. 23/0086-1, UPIN 23104MF2UD01, Precinct 4, MWDBE Contracted Goal: 11%, MWDBE Current Participation: 100%.
end

Background and Discussion:
This project was to purchase and construct a playground structure for Binford Circle Park in Harris County Precinct 4. The project was also to construct a play area with drainage, concrete curb around area with soft landing mulch inside the area. The materials were delayed and the lead time quoted was longer than the contract allowed. To no fault of any party, we are extending the contract days to allow for the extended lead time it took to procure materials and complete the work.

Expected Impact:
This Change in Contract allows Harris County to close this contract with full payment to the contractor for work performed with no fault for material delays incurred.

Alternative Options:
Uphold the original terms and penalize the contractor for items beyond their control.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
08/08/2023
23-4401
Contract Award

Location:
Address (...

Click here for full text