Legislation Details

File #: 24-6553    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/14/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Request for approval of a change in contract with Earth Builders, LP, in connection with John Paul Landing, North Basin Cell, Phase 3, with an addition in the amount of $498,276.00, Job No. 23/0263-1, UPIN 211033020802-3, Precinct 4, MWDBE Contracted Goal: 29%, MWDBE Current Participation: 25.07%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0263, UPIN 211033020802-3
Vendor/Entity Legal Name (if applicable): Earth Builders, LP

MWDBE Contracted Goal (if applicable): 29%
MWDBE Current Participation (if applicable): 25.07%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Earth Builders, LP, in connection with John Paul Landing, North Basin Cell, Phase 3, with an addition in the amount of $498,276.00, Job No. 23/0263-1, UPIN 211033020802-3, Precinct 4, MWDBE Contracted Goal: 29%, MWDBE Current Participation: 25.07%.
end

Background and Discussion:
The project involves constructing the third and final phase of the John Paul Landing Detention Basin master plan. Its goal is to provide a stormwater quality detention pond, achieving the full intended functionality of the basin to enhance drainage and reduce flooding risks. Additionally, it offers opportunities for natural and man-made amenities, including habitat creation, recreational trails, and future community programming. The project is located on the eastern edge of the North Basin Cell and runs north-south alongside Langham Creek.

The change involves an increase of 41,523 cubic yards in detention basin excavation quantities to address the shortage in the original contract excavation amounts. This adjustment will add $498,276.00 to the current contract value, ensuring the project can be completed as originally intended.

Added items:
PCO #1 - Additional Excavation Quantities: (Total Cost: 41523 CY x $12/CY = $498,276.00 / Days: 0)

Expected Impact:
The change allows for the addition of excavation quantities to the contract so the project can be completed in accordance with ...