Legislation Details

File #: 24-6552    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 10/14/2024 In control: Commissioners Court
On agenda: 10/29/2024 Final action: 10/29/2024
Title: Request for approval of a change in contract with Texas Wall & Landscape, LLC, in connection with Townsen Park-n-Ride Multimodal Connector, adding 19 calendar days, with an addition in the amount of $98,306.00, Job No. 23/0268-1, UPIN 14104MF0AV01, Precinct 3, MWDBE Contracted Goal: 3%, MWDBE Current Participation: 0%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0268, UPIN 14104MF0AV01
Vendor/Entity Legal Name (if applicable): Texas Wall & Landscape, LLC

MWDBE Contracted Goal (if applicable): 3%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Wall & Landscape, LLC, in connection with Townsen Park-n-Ride Multimodal Connector, adding 19 calendar days, with an addition in the amount of $98,306.00, Job No. 23/0268-1, UPIN 14104MF0AV01, Precinct 3, MWDBE Contracted Goal: 3%, MWDBE Current Participation: 0%.
end

Background and Discussion:
The project consists of construction of multimodal connector trail that will connect Spring Creek Greenway Hike and Bike trail to Townsen Park and Ride as well as to the historical US-59 bridge crossing the San Jacinto River in Harris County Precinct 3.

Change includes cost and time for installation of permanent casing for 18-inch and 24-inch drill shaft due to sandy soil condition of the site. ($98,306.00 - 15 days).

And change includes time due to flooding and heavy rain. (4 days).

Expected Impact:
The change allows the installation of bridge drill shaft casings due to the sandy soil conditions at the site, and it compensates the contractor for this change.

Alternative Options:
The alternative would be to redesign the foundation altogether and implement the use of spread footings, which would be more costly and time-consuming.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Tak...

Click here for full text