Legislation Details

File #: 24-6382    Version: 1 Name:
Type: Public Necessity Status: Passed
File created: 9/28/2024 In control: Commissioners Court
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Request for approval of a certain project, decreeing the project to be a public necessity and convenience, and directing the Harris County Real Property Division to acquire, one (1) road easement tract for the public project known as Boudreaux Road Segment 3 - from Old Boudreaux Road to 300' west of Hufsmith-Kohrville Road - 2019, for the purpose of roadway construction, UPIN 20104MF1C401, Precinct 3.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Public Necessity

Project ID (if applicable): 20104MF1C401
Vendor/Entity Legal Name (if applicable): Not applicable

MWDBE Contracted Goal (if applicable): Not applicable
MWDBE Current Participation (if applicable): Not applicable
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval of a certain project, decreeing the project to be a public necessity and convenience, and directing the Harris County Real Property Division to acquire, one (1) road easement tract for the public project known as Boudreaux Road Segment 3 - from Old Boudreaux Road to 300' west of Hufsmith-Kohrville Road - 2019, for the purpose of roadway construction, UPIN 20104MF1C401, Precinct 3.
end

Background and Discussion:
This project aims to design a four-lane concrete boulevard with a 32-foot raised median, underground storm sewer system, and pedestrian sidewalk within a 100-foot ROW, transitioning from an existing 14-foot median near Old Boudreaux Road. It includes strategic drainage solutions, intersection improvements, and right-of-way verifications, enhancing safety and integrating with ongoing infrastructure projects.

Expected Impact:
The project is expected to significantly enhance traffic flow, safety, and infrastructure resilience by providing a modern, well-planned boulevard with improved drainage and pedestrian facilities. It will reduce congestion, accommodate future growth, and integrate seamlessly with surrounding projects, contributing to the overall development and sustainability of the area.

Alternative Options:
If no action is taken, this intersection will continue operating under existing conditions.




Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health...

Click here for full text