Title: Request for approval of an award on the basis of low bid to RES Gulf Coast, LLC dba LECON, Inc. in the amount of $158,104 for the construction price, with owner contingency in the amount of $12,628, for installation of 60" reinforced concrete pipe cast iron flap gate with headwall & wingwalls for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received for the construction price (240272), MWDBE Contracted Goal: 15.75%.
Department: Purchasing
Department Head/Elected Official: Paige McInnis

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 240272
Vendor/Entity Legal Name (if applicable): RES Gulf Coast, LLC dba LECON, Inc.

MWDBE Contracted Goal (if applicable): 15.75%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to RES Gulf Coast, LLC dba LECON, Inc. in the amount of $158,104 for the construction price, with owner contingency in the amount of $12,628, for installation of 60" reinforced concrete pipe cast iron flap gate with headwall & wingwalls for the Flood Control District, and for the County Clerk to execute any applicable bonds to be received for the construction price (240272), MWDBE Contracted Goal: 15.75%.
end

Background and Discussion:
The project is a 60" RCP Cast Iron Flap Gate with Headwall & Wingwalls in northeast Harris County. This construction project will remove the damaged 60" Tideflex Valve to P124-00-00 from the adjoining drainage area and replace it with a 60" Cast Iron Flap Gate. This replacement will be in compliance with a settlement to control the flow of offsite drainage to P124-00-00 during high flow events.

Expected Impact:
The existing 60" Tideflex Valve stopped sealing properly. This valve replacement project will remove the damaged flex valve and standardize the operation to a flap gate. The flap gate will be located back into the side berm of the channel to minimize obstruction to flow in P124-00-00 versus the current flex valve position in the center of the channel.

Alternative Options:
There are no viable alternatives to this item being requested. Not approving would allow the existing valve to deteriorate and discharge from P124-00-00 to the adjoining basin, P500-01-00 during peak flows...