Legislation Details

File #: 24-6308    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/27/2024 In control: Commissioners Court
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Request for approval of a change in contract with Formative Structures, LLC, in connection with Barbara Jordan Park - Pavilion and Drainage Improvements - 2021, adding 51 calendar days, with an addition in the amount of $32,970.85, Job No. 23/0352-1, UPIN 21101MF23401, Precinct 1, MWDBE Contracted Goal: 29%.
Department: County Engineer
Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 23/0352
Vendor/Entity Legal Name (if applicable): Formative Structures, LLC.

MWDBE Contracted Goal (if applicable): 29%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Formative Structures, LLC, in connection with Barbara Jordan Park - Pavilion and Drainage Improvements - 2021, adding 51 calendar days, with an addition in the amount of $32,970.85, Job No. 23/0352-1, UPIN 21101MF23401, Precinct 1, MWDBE Contracted Goal: 29%.
end

Background and Discussion:
The original basketball pavilion immediately adjacent to the community center at Barbara Jordan Park was evaluated for structural integrity after damage was observed at the bases of the steel columns. The purpose of this contract change is to reconcile quantities and extend contract duration to fifty-one additional days (thirty days for the drainage system, fourteen days due to inclement weather and park closure and seven days for painting the underside of pavilion.

Expected Impact:
The new pavilion trench drain system will not be completed and visitors will not enjoy the outdoor space and resume community activities previously held once again under the pavilion.

Alternative Options:
Should we not move forward with this change in order we would move forward with a precast system that has ten-month lead time according to Formative Structures, LLC and the pavilion will not be painted. Additionally, there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contr...

Click here for full text