Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): P500-06-00-E006
Vendor/Entity Legal Name (if applicable): Lecon, Inc.
MWDBE Contracted Goal (if applicable): 17%
MWDBE Current Participation (if applicable): 45.14%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 3 with Lecon, Inc., for the Lauder Stormwater Detention Basin - Phase 2, resulting in an addition of $4,083.01 to the contract amount (Greens Bayou Watershed, Bond ID C-34, Project ID P500-06-00-E006, Job No. 22/0224, Precinct 2, MWDBE Contracted Goal: 17%, MWDBE Current Participation: 45.14%).
end
Background and Discussion:
This change in contract is needed to complete the construction contract for this project. Lauder Stormwater
Detention Basin - Phase 2 includes excavating the southern compartment of a stormwater detention basin within the former Castlewood subdivision to reduce flooding along the P138-00-00 channel that drains to Greens Bayou. The purpose of this contract change is to add items and contract language required for Texas Water Development Board (TWDB) grant funding, as well payment for a contractor provided mussel survey.
Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.
Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
...
Click here for full text