Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 21/0369, UPIN 22101MF25X01
Vendor/Entity Legal Name (if applicable): Statewide Traffic Signal Co.
MWDBE Contracted Goal (if applicable): 17.50%
MWDBE Current Participation (if applicable): 15.06%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Statewide Traffic Signal Co., in connection with final construction of Traffic Signal - Riverstone Ranch Dr at Hughes Rd - 2021, adding 48 calendar days, with an addition in the amount of $5,441.58, Job No. 21/0369-1, UPIN 22101MF25X01, Precinct 2, MWDBE Contracted Goal: 17.50%, MWDBE Current Participation: 15.06%.
end
Background and Discussion:
The project involves constructing a new traffic signal system and pedestrian ramps at the intersection of Riverstone Ranch Drive and Hughes Road.
Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.
- Final Adjustments $5,441.58
Changes also include added 48 calendar days as follows:
- PCO - 1 Additional 14 days to relocate Run #22 and Run #36 due to utility conflict. - $0.00 - 14 days
- PCO - 2 Additional 15 days to relocate Pole #4 and Pole #2 due to utilities (AT&T, Sewer line, water line) - $0.00 - 15 days
- PCO - 3 To add 19 days for waiting on CPE Power connection. - $0.00 - 19 days
Expected Impact:
Changes allow for addition of new bid items to complete the project in accordance with the original intent of the project and in compliance with precinct requests.
Alternative Options:
Revise original scope of the project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X_ Transp...