Legislation Details

File #: 24-6046    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 9/20/2024 In control: Commissioners Court
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Request for approval of a change in contract with Conrad Construction Co., Ltd. in connection with Anderson Road - Hiram Clarke Road to Almeda Road - 2018, adding 33 calendar days, with an addition in the amount of $182,015.00, Job No. 23/0152-3, UPIN 19101MF0XY01, Precinct 1, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 0%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0152, UPIN 19101MF0XY01
Vendor/Entity Legal Name (if applicable): Conrad Construction Co., Ltd.

MWDBE Contracted Goal (if applicable): 21%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Conrad Construction Co., Ltd. in connection with Anderson Road - Hiram Clarke Road to Almeda Road - 2018, adding 33 calendar days, with an addition in the amount of $182,015.00, Job No. 23/0152-3, UPIN 19101MF0XY01, Precinct 1, MWDBE Contracted Goal: 21%, MWDBE Current Participation: 0%.
end

Background and Discussion:
Project includes completion of the two-lane concrete curb and gutter road with sidewalk on both sides and left turn lanes at the intersections approximately 7,800 linear feet of Anderson Road construction from 500 feet west of Hiram Clark Road to Almeda Road/FM 521 (Segment 2).

This change in contracts includes:

The increase in existing line items as well as the addition of new line items to relocate an existing 12" AC waterline. ($163,850.00 - 31 days)

The addition of new scope item to modify a Type A inlet. ($18,165.00 - 2 days)

Expected Impact:
Changes allow for compensation to the Contractor for actual quantities used in construction, in accordance with the original intent of the project.

Alternative Options:
Revise original scope of the project.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
x Transportation
_ Flooding
x Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
06/27/2023
23-3490
Contract Award
06/25/2024
24-3586...