Title: Request for approval to execute an agreement with IDS Engineering Group, Inc., in the amount of $125,622.24 for Construction Phase Services in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, UPIN 22102MF2G801, Precinct 2, MWDBE Contracted Goal: 20%.
Sponsors: Mony Hossain
Attachments: 1. 24-5259-Award-UPIN 22102MF2G801-CPS-Vickery Intersection-IDS-P2-08-27-2024
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 22102MF2G801
Vendor/Entity Legal Name (if applicable): IDS Engineering Group, Inc.

MWDBE Contracted Goal (if applicable): 20%
MWDBE Current Participation (if applicable): 0%
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with IDS Engineering Group, Inc., in the amount of $125,622.24 for Construction Phase Services in connection with Intersection Improvement - Vickery Street at Lauder Road - 2021, UPIN 22102MF2G801, Precinct 2, MWDBE Contracted Goal: 20%.
end

Background and Discussion:
The project is in North Harris County in the Green's Bayou and Hall's Bayou watershed, south of Beltway 8, east of Highway 69. The project consists of Intersection improvements including sidewalks, roadway widening, and the installation of a new traffic signal. The project limits include the intersection of Vickery Street and Lauder Road with approximately 870 feet of roadway improvement at Lauder Rd, 300 feet at Vickery Street and 800 feet at WE Crowley Park Road.

Expected Impact:
This project seeks to enhance vehicular mobility by improving roadway conditions along Vickery Street, Lauder Road, and WE Crowley Park Road. The Goal of the project is to improve overall pedestrian and vehicular mobility in the area.

Alternative Options:
If no action is taken, the project may experience delays in improving mobility in the area.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
12/14/2021
21-6764
Request for approval to negotiate with IDS Engineering...

Click here for full text