Legislation Details

File #: 24-5245    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 8/16/2024 In control: Commissioners Court
On agenda: 8/27/2024 Final action: 8/27/2024
Title: Request for approval to execute an agreement with B2Z Engineering, LLC in the amount of $250,000.00 for Professional On-Call Engineering Services for Construction Materials Testing in connection with various projects in Harris County, UPIN 24104MF3FF01, Precinct 4, MWDBE Contracted Goal: 17.50%.
Sponsors: Mony Hossain
Attachments: 1. 24-5245-Consultant -UPIN 24104MF3FF01-B 2 Z consultant Precinct 4 On Call PSA agreement

Harris County Commissioners Court
Request for Court Action
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award

Project ID: UPIN 24104MF3FF01
Vendor/Entity Legal Name: B2Z Engineering, LLC

MWDBE Contracted Goal (if applicable): 17.50%
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above.

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with B2Z Engineering, LLC in the amount of $250,000.00 for Professional On-Call Engineering Services for Construction Materials Testing in connection with various projects in Harris County, UPIN 24104MF3FF01, Precinct 4, MWDBE Contracted Goal: 17.50%.
end

Background and Discussion:
The agreement would be for Professional On-Call Engineering Services for Construction Material Testing to facilitate the delivery of various projects within Harris County Precinct 4.

Expected Impact:
This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt and various other construction materials to ensure the material's compliance with Harris County Engineering Department's adopted standards and specifications as required by state law.

Alternative Options:
Project specific consultants would need to be sought out for the different projects.

Alignment with Goal(s):
X Justice and Safety
X Economic Opportunity X Housing
_ Public Health X Transportation X Flooding
X Environment

X Governance and Customer Service

Prior Court Action (if any):

Date
Agenda Item #
Action Taken
06/04/2024
139
Authorization to Negotiate Approved

Location: Within Precinct 4 Address (if applicable):
Precinct(s): Precinct 4

Fiscal and Personnel Summary
Service Name


Current Fiscal Year Cost
Annual Fiscal Cost

Labor
Non-Labor
Total
Recurring Expenses
Funding Sources
...

Click here for full text