Department: Toll Road Authority
Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): Southwestern Bell Telephone Company, LLC, dba AT&T
MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Request Summary (Agenda Caption):
title
Request for approval to execute a utility construction service agreement with Southwestern Bell Telephone Company, LLC, dba AT&T Texas, for relocation of utility services for the State Highway 225/Sam Houston Tollway East Interchange construction project in the amount of $1,069,766.65 (Precinct 2).
end
Background and Discussion:
The proposed adjustments will replace / relocate existing Southwestern Bell Telephone Company, LLC facilities that conflict with the proposed State Highway 225 / Sam Houston Tollway East Interchange construction project. The adjustment includes underground telecommunication facilities.
After completion of the construction services, if the estimated cost is less than the estimated amount, Southwestern Bell Telephone Company, LLC will refund or credit the difference. If actual cost of the construction services is more than the estimated cost, Southwestern Bell Telephone Company, LLC will invoice the difference, which would require a future Court action.
Expected Impact:
The Agreement allows Southwestern Bell Telephone Company, LLC to expedite the telecommunication underground line adjustments, minimizing the risk of construction delays for the Project.
Alternative Options:
No other recommended services for this identified need.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court ...
Click here for full text