Title: Request for approval of a change in contract with DVL Enterprises, LLC, in connection with Sidewalks and Undercrossing Project - Fry, adding 46 calendar days, with an addition in the amount of $21,510.00, Job No. 23/0117-2, UPIN 20103N302902, Precinct 4, MWDBE Contracted Goal: 33%, MWDBE Current Participation: 18.28%.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0117, UPIN 20103N302902
Vendor/Entity Legal Name (if applicable): DVL Enterprises, LLC

MWDBE Contracted Goal (if applicable): 33%
MWDBE Current Participation (if applicable): 18.28%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with DVL Enterprises, LLC, in connection with Sidewalks and Undercrossing Project - Fry, adding 46 calendar days, with an addition in the amount of $21,510.00, Job No. 23/0117-2, UPIN 20103N302902, Precinct 4, MWDBE Contracted Goal: 33%, MWDBE Current Participation: 18.28%.
end

Background and Discussion:
The project is for the construction of sidewalk on Fry Road between Saums Road and Park Row Road within Harris County, Precinct 4. The project is intended to improve and unsure reliable and safe routes of transportation to residents of the Harris County. This change in contract includes the addition of missing items to the contract for an additional amount of $21,510.00 to the current contract value so the project can be completed in accordance with the original intent.
Added items:
(PCO #2) - Wall removal and disposal Sta 13+00 RT - $3,550.00, additional 2 days
(PCO #3) - Driveway # 25 Automatic Gate adjustment Sta 24+00 LT - $3,000.00, additional 2 days
(PCO #4) - Driveway # 59 Automatic Gate adjustment Sta 11+50 RT - $7,480.00, additional 21 days
- Driveway # 60 Automatic Gate adjust...