Legislation Details

File #: 24-5133    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 8/14/2024 In control: Commissioners Court
On agenda: 8/27/2024 Final action: 8/27/2024
Title: Transmittal by the Flood Control District of a preliminary engineering report by McDonough Engineering Corporation dated May 15, 2024, and titled Friendswood Regional Stormwater Detention Basin (Clear Creek Watershed, Bond ID CI-62, Project ID A500-09-00-E001, Precinct 2).
Attachments: 1. 082724 TRANSMITTAL PER A500-09-00-E001 backup PCT 2.pdf
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): A500-09-00-E001
Vendor/Entity Legal Name (if applicable): McDonough Engineering Corporation

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of a preliminary engineering report by McDonough Engineering Corporation dated May 15, 2024, and titled Friendswood Regional Stormwater Detention Basin (Clear Creek Watershed, Bond ID CI-62, Project ID A500-09-00-E001, Precinct 2).
end

Background and Discussion:
This is a partnership project between the City of Friendswood, Galveston County, Galveston Consolidated Drainage District, and the Flood Control District. The objective of this project is to reduce peak flows and decrease the water surface elevation along Clear Creek Channel (A100-00-00). Three alternatives were evaluated during the PER phase and alternative 2 has been selected, which is a dry bottom basin that provides total 710 acre-feet of storage volume.

Expected Impact:
Benefits for alternative 2 include removing 87 structures from the floodplain, 97 acres from the inundation area and 0.7 miles of roadway for the 100-year storm event.

Alternative Options:
The alternative should the PER not be accepted is the Flood Control District will not be able to proceed with design and construction of the project and flood risk will remain the same.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any): N/A
Date
Agenda Item #
Action Taken




Location:
Address (if applicable): 2501 Dixie Farm Road, ...

Click here for full text