Title: Request for approval of a utility adjustment agreement with Comcast of Houston, LLC, in the amount of $137,924.03 for the adjustment of facilities at the proposed HCFCD Unit E121-00-00 basins upstream of West Little York (White Oak Bayou Watershed, Bond ID C-15, Project ID E500-25-00-E001, Agreement No. 2023-24, Precinct 1).
Department: Flood Control District
Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): E500-25-00-E001
Vendor/Entity Legal Name (if applicable): Comcast of Houston, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request

Request Summary (Agenda Caption):
title
Request for approval of a utility adjustment agreement with Comcast of Houston, LLC, in the amount of $137,924.03 for the adjustment of facilities at the proposed HCFCD Unit E121-00-00 basins upstream of West Little York (White Oak Bayou Watershed, Bond ID C-15, Project ID E500-25-00-E001, Agreement No. 2023-24, Precinct 1).
end

Background and Discussion:
The Arbor Oaks Stormwater Detention Basin is a proposed regional flood risk reduction project in the White Oak Bayou watershed. This project is part of the ongoing CDBG-DR program. The agreement will allow for the safe removal of certain facilities so that construction can occur. This project occurs in the 3rd quartile under the 2022 Prioritization Framework approved by Commissioners Court.

Expected Impact:
Upon execution of the utility adjustment agreement, the utility will undertake removal of the facilities allowing for the safe construction of the project stormwater detention basins.

Alternative Options:
If no action is taken flood risks will remain the same. Additionally, the project utilizes federal funds, so delays could impact the funding of the project.

Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
X Flooding
_ Environment
_ Governance and Customer Service

Prior Court Action (if any):
Date
Agenda Item #
Action Taken




Location:
Address (if applicable):
Precinct(s): Choose an item.

Fiscal and Personnel Summary...

Click here for full text