Legislation Details

File #: 24-5108    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 8/14/2024 In control: Commissioners Court
On agenda: 8/27/2024 Final action: 8/27/2024
Title: Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Crosby Lynchburg Road Phase 3, with an addition in the amount of $175,072.94, Job No. 21/0059-10, UPIN 17102MF0MV01, Precincts 2 & 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0059, UPIN 17102MF0MV01
Vendor/Entity Legal Name (if applicable): SER Construction Partners, LLC

MWDBE Contracted Goal (if applicable): N/A
MWDBE Current Participation (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with SER Construction Partners, LLC, in connection with Crosby Lynchburg Road Phase 3, with an addition in the amount of $175,072.94, Job No. 21/0059-10, UPIN 17102MF0MV01, Precincts 2 & 3, Justification for 0% MWDBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end

Background and Discussion:
Project includes the reconstruction of approximately 1.85 miles of Crosby Lynchburg Road (FM 2100) from Magnolia Drive south to Lochness Drive and includes the widening of the bridge over HCFCD Channel G103-05.

Change includes:
- Remove and reinstall 150 LF of MBGF and 1 EA Guardrail Terminal Section installed by the previous contractor to facilitate the installation of slope pavement. - $5,277.78 - 0 days.
- Per Precinct 3's request, paint the concrete wingwalls and pedestrian rail along the bridge, as well as the small section of rail along the headwall at Station 35+93 RT on the project. - $19,015.30 - 0 days.
- Replace failing joint sealants originally placed by the previous contractor. - $10,200.00 - 0 days.
- Per Precinct 3's request, convert ten (10) Type A inlets to Modified Type A inlets. - $55,148.30 - 0 days.
- Plans are missing to call out for inlet adjustments that are required based on the field conditions. - $13,997.60 - 0 days.
- For drainage improvement and ease of maintenance, remove unn...