Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): UPIN 22101MF2F101
Vendor/Entity Legal Name (if applicable): EJES Incorporated
MWDBE Contracted Goal (if applicable): 100%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a Study Report prepared by EJES Incorporated for Asphalt Project - Forest Acres Subdivision, UPIN 22101MF2F801, Precinct 1.
end
Background and Discussion:
Precinct 1 has continued to develop their roadway rehabilitation program and is preparing to improve roadways along Forest Acres Subdivision. Project consists of roadside ditch improvements, rehabilitation, or full depth reconstruction of approximately 15,140 ft (2.87 Miles) of asphalt roadway. The overall scope of the project is to improve the roadways safety of the roadway users. The scope also included improvements to the existing open roadside ditches, drainage outfalls, and culvert replacements, as needed, to ensure capacity and positive drainage. This study report includes an executive summary with all supporting appendices of details describing the analysis and recommendations from the study phase services including surveying, geotechnical, Utility Conflict table, Traffic Control, and drainage to be utilized for the proposed design of the project.
Expected Impact:
Reconstruction and rehabilitation of the proposed roadways will improve drainage and pavement conditions.
Alternative Options:
If no action is taken; the proposed roadway improvements will be delayed. No alternative to improvement to asphalt reconstruction project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and C...