Department: County Engineer
Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 23/0197
Vendor/Entity Legal Name (if applicable): Formative Structures, LLC
MWDBE Contracted Goal (if applicable): 27%
MWDBE Current Participation (if applicable): 17%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Formative Structures, LLC, in connection with Mercer Botanic Gardens - Restroom Reconstruction-2022, adding 28 calendar days, with an addition in the amount of $7,336.86, Job No. 23/0197, UPIN 23103MF2VX01, Precinct 3, MWDBE Contracted Goal: 27%, MWDBE Current Participation: 17%.
end
Background and Discussion:
The existing restroom building at Mercer Botanic Gardens is a wood-framed building constructed in or around 1977, with an addition added to the building sometime later. The blue building is in the 100-year floodplain and in poor condition. This change in contract includes adding a handrail system to meet requirements of the Americans with Disabilities Act of 1990 and Texas Department of Licensing and Regulations.
Expected Impact:
This court action would account for necessary changes to the project schedule and meet requirements of the Americans with Disabilities Act of 1990 and Texas Department of Licensing and Regulations.
Alternative Options:
Should we not move forward with this change in order we would revise the design layout, remove existing concrete, and install new concrete that meets federal and state disability standards which would have a significant cost and schedule impact to this project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
_ Transportation
_ Flooding
_ Environment
X Governance and Customer Service
Pr...