Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 21/0408, UPIN 201033952823
Vendor/Entity Legal Name (if applicable): WadeCon, LLC
MWDBE Contracted Goal (if applicable): 13%
MWDBE Current Participation (if applicable): 11.99%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with WadeCon, LLC in connection with Greenhouse Road-North Approach Cypress Creek Bridges To Mound Road; Mound Road-458ft East Of Crossland Park Lane To Greenhouse Road - 2020, with an addition in the amount of $119,848.60, Job No. 21/0408-3, UPIN 201033952823, Precinct 3, MWDBE Contracted Goal: 13%, MWDBE Current Participation: 11.99%.
end
Background and Discussion:
Project includes completion of the second half of the concrete boulevard pavement section for Greenhouse Road, from North Approach Cypress Creek Bridges to Mound Road and Mound Road and from 458ft East of Crossland Park Lane to Greenhouse Road.
This change in contracts includes Cost of overrun and underrun of bid items based on the actual quantities of materials furnished and installed on the jobsite. ($119,848.60 - 0 days).
Expected Impact:
Change allows unused funds to be returned to Harris County and allows the Contractor to be compensated.
Alternative Options:
Maintain the original scope of the project.
Alignment with Goal(s):
_ Justice and Safety
_ Economic Opportunity
_ Housing
_ Public Health
X Transportation
_ Flooding
_ Environment
_ Governance and Customer Service
Prior Court Action (if any):
Date
Agenda Item #
Action Taken
01/25/2022
22-0404
Contract Award
01/31/2023
23-0652
Contract Amendment for additional funds and extension of project term
03/26/2024
24-1547
Contract Amendment for additiona...